Saturday, December 31, 2011

Spring weather....

Spring-like weather has allowed the crew to continue working on some of the outside projects. I arrived at 8:30 this morning to see the concrete truck in front of the house.  They poured the front concrete stoop and the walkway pavers leading to the front side walk.  It will be great to be able to walk on a paved surface instead of a muddy walkway.  River rock will surround the pavers to finish off the walkway.  
concrete pavers leading to front entry stoop


At 9:45 am I headed towards Schaumburg to visit that Swedish design center, also known as IKEA.  It was a successful shopping excursion.  Seven wood / glass linear style kitchen wall cabinets were purchased to provide a contrast to the dark maple base cabinets.  Economically priced at $ 98...but some assembly is required.  Several light fixtures were also obtained for the bedrooms and storage areas.  We'll need to make another trip in a few weeks to get bathroom accessories and more light fixtures.

Some miscellaneous interior framing was completed this week. Kitchen soffits and the attic storage room were framed. And a small closet was built in the second floor Den / Nursery adding to the functionality of this room. The exterior wallcavities were filled with batt insulation and are now ready for the gypsum board.
Next week should see the start of the siding, installation of dry-wall and the construction of the exterior deck and trellis.  Were making great progress and the final month will be exciting.

H A P P Y    N E W    Y E A R!   I'm looking forward to 2012.