The past few weeks the crew has been installing wall and floor finishes in the bathrooms, laundry and first floor. Ceramic and porcelain tile was selected and installed in the two second floor bathrooms and marble was used for the powder room. The master bathroom shower area came out looking very clean and modern through the use of 6" x 24" plank tiles stacked vertically with 12" x 24" planks for the floor.
Due to the age of the building, the first floor had a few areas which were uneven and slightly sloped. A condition which is pretty common for vintage buildings. This was fixed by placing wood sleepers (cut with a slope) and new 3/4" plywood over the entire floor area. This level sub-floor was then ready for the pre-finished, carbonized bamboo flooring. It is now installed and it looks great! Slate and marble tile was installed in the front entry. The existing stair was refurbished with new oak treads and painted risers. All the floor and wall finishes have come out exceptional.
new bamboo flooring |
The exterior siding is installed but some of the corner trim boards still need to be completed.
I'm working on the finalizing the Family Room fireplace / storage design. The west wall will have a modern gas fireplace with built-in shelving and a raised, horizontal concrete hearth. Mosaic tile will surround the firebox and wood trim will finish off the entire area. Painted wood shelving will provide areas for accessories, books and electronics. There are provisions for a flat-screen television which could be placed directly above the fireplace.
The interior will be primed tomorrow and painted by the end of the week. The cabinets and vanities will be installed Wednesday. Set-up for the terrazzo counters will begin Thursday with the concrete pouring to take place on Saturday.
The lighting and plumbing fixtures will be installed this week. The deck and trellis will be completed next week -- just in time to enjoy our Spring weather. Carpet installed next week. Finishing touches and staging the second week of February.